Note from Andrew Herbert

Dear Timbertop Residents,

 

I am pleased to provide you with the latest construction update for May. There is plenty to talk about with development full steam ahead on so many different aspects of the site.

 

The entrance to the estate is forever evolving and really taking shape around the previous land sales office. The Timbertop Cafe, being built on this location, has commenced construction after a long planning process and it is anticipated to be open in July.

 

Almost 300 new home sites have been sold within Timbertop. The Grasslands and Outlook Release are now sold out and The Picnic Release has sold over 50% of lots, showcasing a positive response to the latest releases. The development team have a busy 6 months ahead.

 

In the short term, we are working towards releasing the next stage featuring a selection of 700m2 park fronted lots.

 

To add to the project, we are pleased to announce that plans have been submitted to council for a 2 hectare park in the heart of Timbertop. Within the coming weeks a 2D coloured plan will be available from the land sales office, highlighting the key park features. Some of these will include a large kick-about area, basketball half-court and a large children’s playground. Stay tuned for further announcements!

 

For more information on any development or sales updates please visit the Timbertop sales office at 9 Penshurst Crescent, Officer VIC 3809.

 

Kind regards,

Andrew Herbert

 

The Park and Fields Release

Works onsite have been forging ahead with the majority of service works now completed. The concrete footpaths, curb and channel works have been mostly completed and the final touches to the decorative rock retaining walls are in progress.

Street lights have been installed and the asphalt works will commence within the next few weeks. We anticipate a timetable of key delivery dates for Stage 5 as follows: Practical completion of Civil Works in June/July 2015 with Title Registration in August 2015.

 

The Grasslands Release

The bulk earthworks and majority of service works below the surface are now complete. Work has commenced on the concrete footpaths, curb and channel. The retaining wall contractors will also commence work within this stage in the next few weeks.

We anticipate a timetable of key delivery dates for Stage 5A as follows: Practical completion of Civil Works in July/August 2015 with Title Registration in August/September 2015. Best endeavours will be made to expedite these dates and work is progressing quickly onsite.

The Outlook Release

As an exclusive release of only 11 park fronted allotments, the bulk earthworks are progressing rapidly and largely completed. With all construction plans approved, work is commencing on the installation of services and retaining walls. The remaining site works for stage 7 are expected to be completed in September, with the final documentation for the statement of compliance pushing title registration into October 2015.

The Picnic Release

Preliminary bulk earthworks have commenced and we have recently obtained approved construction plans from council. The final site works for stage 6 are expected to be completed towards the end of 2015, with the final documentation for the statement of compliance pushing title registration into December 2015/January 2016.