Construction Update – December 2016

It has been an incredibly busy past few months at Timbertop Estate as we begin to wrap up the year and prepare for 2017. With this, there have been some exciting construction updates:

 

 

Stage 20 – The Orchard Release (Lots 2001 to 2038)

Construction now complete. Title Registration occurred in November 2016

 

Stage 6A & R –  The Leisure Release (Lots 636 to 667)

Construction 90% complete. Completion expected late 2016. Title Registration & Settlements estimated for early 2017.

 

Stage 10 – The Sanctuary Release Part 1 (Lots 1001 to 1046)

Construction 80% complete. Asphalt works commencing January 2017. Completion expected late-January 2016. Title Registration & Settlements estimated for February 2017.

 

 

Stage 10A – The Sanctuary Release Part 2 (Lots 1047 to 1062)

Construction commenced December 2016. Title Registration & Settlements estimated for July/August 2017.